PORTFOLIO

BUILDING

PROJECT DETAILS

  • Client: Confidential Client
  • Project: MSA1A
  • Location: Mesa, Arizona
  • Square Feet: 170K
  • Construction Volume: $750M
  • Category: Private, Mission Critical, Commissioning

ABOUT THIS PROJECT

MSA1A is the first phase on a 240MW hyper-scale data center campus in Mesa, AZ. CriticalArc has been brought on as the 3rd Party QA and Commissioning Provider to perform Level 1 through Level 5 services for the first 40MW buildout of a 77MW facility. Our scope includes the commissioning of all mechanical, electrical distribution, security, fire alarm, and fire suppression systems. The project is estimated to be $750M in construction volume and is scheduled to be completed in the first quarter of 2025.