PORTFOLIO
BUILDING

PROJECT DETAILS
ABOUT THIS PROJECT
Working for the onsite GC Commissioning team, Fortis Construction, CriticalArc is performing pre-commissioning activities on a 60 MW per building Data Center campus in Los Lunas. CriticalArc has been tasked with all commissioning-related activities including, participating in daily Cx morning meetings, reviewing the status of electrical equipment documentation & readiness using BIM360, and continual review of project specifications & electrical drawings using ProCore, and assisting with pre-energization walks of various electrical equipment. CriticalArc’s scope has been extended through 2024.
Image Credit: bizjournals.com