ABOUT THIS PROJECT
The Denver International Airport added 16 new gates to Concourse A. CriticalArc was contracted to Turner Flatiron – Joint Venture in the role of commissioning and QA/QC support on this $700M project, which achieved a LEED Gold certification from the USGBC. We assisted with the coordination of pre-functional and functional testing of mechanical, electrical and plumbing systems for a seamless transition to the Owner’s commissioning group. The commissioning duration was 7 months and was completed during the summer of 2022.