  • Client: Fort Lauderdale International Airport
  • Project: Terminal 4 Gate Replacement (ongoing)
  • Location: Fort Lauderdale, FL
  • Construction Volume: $500M
  • Category: Public, Aviation

ABOUT THIS PROJECT

The FLL project is a $500M gate expansion on Terminal 4. The commissioning scope consists of nine passenger boarding bridges, inclusive of their PCAir, ground power units and potable water cabinets, security systems (ACS & CCTV) commissioning and all project commissioning documentation (final commissioning reports, systems manual, etc.) CriticalArc was hired to assist Turner Construction with specialty commissioning services and documentation. The project duration is 4 years and is scheduled to finish in 2021, earning a LEED designation.

 